AGBU School Manoukian Center’s Construction Have Finished

AGBU school Manoukian Center-1Manoukian Center by John Sergio Fisher & Associates.

AGBU School Manoukian Center’s Construction finished

The construction of this 23,000 SF school renovation has finished. It started on March 2014 and finished by September 2017.

The glass envelope of the new lobby and foyer is been closed up and the crew started working on the interior finishes (metal cladding, ceiling, paint, etc.) On the audience chamber 95% of the wood paneling is in place and the acoustical treatment installation should start shortly. Seating risers should be built up within next month in preparation for the seating installation some time during the summer.  

Read More >

Previous Post›
Next Post›
BACK TO What's New›